Final onshore modules arrive onsite for Ichthys LNG Project

Posted 5 September 2016

The INPEX-led Ichthys LNG Project reached a significant milestone today with the arrival of the final three modules required to complete construction of the </span >Project’s onshore processing facilities in Darwin, Northern Territory, Australia.

The modules—</span >very large assemblies of structural, piping and mechanical equipment</span >—</span >will next be connected with other modules to complete the two LNG processing trains on site.

These trains will liquefy gas transported to Bladin Point, Darwin via an 890- kilometre gas export pipeline from the Ichthys Field off the West Australian coast.

Ichthys Project Managing Director Louis Bon said the safe arrival of the last modules marked a key milestone in the development of a very complex and challenging project.

“In total, 230 modules have arrived from the Project’s four fabrication yards in </span >Thailand, China and the Philippines. The team has done an outstanding job in </span >shipping them to Darwin and safely installing them onsite,” he said.

“This is particularly impressive, given some modules weighed in excess of 5500 </span >tonnes and measured more than 90 metres long.

“Mastering the design and fabricatio</span >n of the modules in huge yards overseas and then shipping them to site is critical for the efficient and effective delivery of such a large and complex project.

“Overall, the Project’s onshore facilities were designed so that some elements </span >are modularised and others are stick-built onsite in Darwin,</span >” Mr Bon said.

For the past two years, pre-fabricated modules have regularly sailed through </span >Darwin Harbour on their way to the Project’s module offloading facility (MOF) at </span >Bladin Point.

The MOF enables the safe delivery of large modules and oversized equipment, too large to be transported to site by road.

Self-propelled modular transporters with more than 400 axle lines were used to move the modules to their final location on the Bladin Point site.

Mr Bon said the arrival of the last modules signified the Project had entered the final phase of construction and the focus would now move to testing, commissioning and start-up.</span >

“The significance of this milestone cannot be over</span >-stated—the modules are key compon</span >ents of the Project’s processing facilities, which will eventually produce up to 8.9 million tonnes of LNG and 1.6 million tonnes of LPG per annum.”

"The Ichthys LNG Project will create opportunities and deliver significant long- term benefits for Australia during its forty years of operations."

ENDS

Media enquiries: Janet Pinheiro +61 (0) 407 615 450.